OUTLINE
Introduction: A Historical Contexts
Safety Justification Report of the Ignalina NPP (TOB)
"In-Depth Safety Assessment of the Ignalina NPP" Project
Recommendations of the Ignalina Safety Panel
Follow-up Safety Analyses of the Ignalina NPP
Ignalina PSA Level 1 Project
Conclusions
Introduction: A Historical Contexts
Since commissioning of the Ignalina NPP in 1983 a number of the safety analyses have been conducted.
1988 - Safety Justification Report of the Ignalina NPP (TOB)
1992-96 - Level 1 Probabilistic Safety Assessment of the Ignalina NPP
1996 - Evaluation of the RBMK-1500 Accident Confinement System
1995-96 - In-Depth Safety Assessment of the Ignalina NPP (SAR)
1995-97 - Review of the Safety Analysis Report (RSR)
1997-99 - Safety analyses recommended by SAR, RSR and Ignalina Safety Panel
Safety Justification Report (TOB)
Safety Justification Report of the Ignalina NPP has been issued shortly after Chernobyl accident
Issues discussed in the TOB are limited by System Descriptions and Accident Analysis
Accident Analysis in the TOB have been performed for design power level of 4800 MW
Russian developed computer codes which were never been widely validated to demonstrate that its are adequately represent a reality have been used for analysis.
In-Depth Safety Assessment Project (1)
This is the first attempt to perform Western-style safety analysis for any Soviet-design NPP
The assessment consists of two elements: the Safety Analysis Report (SAR) and independent Review of the Safety Report (RSR)
A panel of international nuclear safety experts, the Ignalina Safety Panel, was established with aim to monitor and supervise the scope and production of the SAR and its review process and to make an independent recommendations to the Lithuanian Government, Ignalina NPP, VATESI and donor countries regarding continues plant operation and implementation strategies for the SAR and RSR recommendations.
In-Depth Safety Assessment Project (2)
The objectives of the SAR were:
- to demonstrate that the plant is adequately safe;
- to identify and evaluate any factors which may limit the safe operation of the plant in the foreseeable future;
- to assess the plant's safety standards and practices, recommend and additional improvements which are reasonable practicable and provide estimates of their cost and schedules
In-Depth Safety Assessment Project (3)
The SAR project was organised in 10 Task Groups and the RSR structure reflected this. The groups were:
TG1 Plant Description
TG2 History of Safety and Performance
TG3 Fault Schedule
TG4 System Analysis
TG5 Accident Analysis
TG6 Equipment Qualification
TG7 Management of Ageing
TG8 Role of Operator
TG9 Safety Management
TG10 Demonstration of Acceptability
Fault Schedule (TG3)
Objective: Demonstration that all faults are either
The analyses have shown that the Ignalina NPP protective systems are adequate to bring the plant into a safe state following one of the assumed initiators, provided that operator actions occur within about 10 minutes.
A number of events typically considered in Western SARs were not analysed or considered.
Loss of Coolant Accidents (1)
In general Ignalina NPP is adequately protected against breaks that occur in the reinforced leak-tight compartments if they do not result in local flow degradation.
Some LOCA sequences may lead to low flow conditions requiring either faster Emergency Core Cooling System activation or increased injection rates to avoid cladding temperature excursions.
Loss of Coolant Accidents (2)
The SAR analyses of LOCAs revealed several plant deficiencies. Some
Plant Modifications are required:
- Installation of an early ECCS initiation signal to compensate for stagnation flow in a GDH, based on low flow in multiple channels.
- Installation of new reactor trip and ECCS initiating signals to compensate for breaks outside the confinement, based on the dP/dt signal in the drum separator.
- Modifications which ensure that the emergency core cooling water is delivered to the affected reactor half.
Further
analysis is required to support the proposed hardware installations and to resolve critical issues.
Multiple Pressure Tube Ruptures Issue
Recommendations on the safety Improvements at the Ignalina NPP concerning MPTR issue:
A reactor scram actuation on "low flow" in a few channels connected to one GDH must be installed as soon as possible.
ECCS initiation should be derived on reactor scram on "low flow".
Further
analysis is required to support the proposed hardware installations and to resolve MPTR critical issues.
Reactivity Initiated Accidents
Acceptance criteria met, even if single failures are assumed.
Major Issue
- Several fuel bundles of a new type were loaded into the Ignalina Unit 1 and Unit 2 core since 1996
- Increased enrichment of 2.4 % U-235 and contain Erbium as burnable poison.
- Issue not addressed in the SAR.
Further
analysis is required.
Steam Line Failures
The SAR analysts propose a number of hardware modifications and changes in regulations and procedures to overcome the design weaknesses and to better protect the surrounding population against radiological exposures after Steam Line rupture events, first of all
- providing early, automatic reactor trip and emergency coolant injection for all break locations.
Further
analysis is required to support the proposed hardware installations and to resolve critical issues.
Anticipated Transients Without Scram
For RBMK reactors ATWS are not design basis accidents and no previous analyses of such accidents were performed. The ATWS studies in the Ignalina SAR are the first of the kind of for RBMK reactors.
These analyses have a different purpose from DBA studies. The purpose of the ATWS studies in SAR was to identify the need for possible future design modifications to the shutdown system, to determine the minimum time available for accident mitigation and to make a step towards developing accident management measures and procedures.
The SAR analysis shows that some ATWS scenario can lead to unacceptable consequences.
ATWS (2)
The apparent lack of the effective inherent safety features in RBMK reactors leads to one high priority recommendation, that a second fast acting, independent and fully diverse reactor shutdown system needs to be installed. However, development and implementation of the second shutdown system requires 3-4 years.
VATESI has required Ignalina NPP to develop and implement a compensatory measures for existing CPS/EPPS
Major Safety Issues Originated from SAR
Second Shutdown System
CPS compensatory measures
Reactor scram and ECCS actuation on low flow in one GDH
Reactor scram and ECCS actuation on dP/dt signal in drum separator
ALS Safety Case
RCS Safety Case
Additional Accident Analysis
Safety analyses for core with new fuel design
Follow-up Safety Analyses
1997 - the Safety Case for the CPS has been completed
1997-98 - the Safety Cases for structural integrity of the reactor cooling system the accident localisation system have been developed
1997-98 - Analytical base for development of the additional shutdown system DAZ as well as Safety Case for DAZ system have been developed
1997-99 - Safety analyses for core with new fuel design have been continuously performed before loading of new party of fuel into the core
1998-99 - Analytical bases for implementation of proposed modifications concerning new signals for early actuation of reactor trips and ECCS well as Safety Cases for these modifications have been developed
DAZ Project (1)
Lithuanian Regulatory Body VATESI has required Ignalina NPP to develop and implement a compensatory measures for Control and Protection System before Unit 1 will be allowed to restart from its 1998 outage.
Joint Lithuanian - USA project for development and implementation of RBMK-1500 Additional Shutdown System (DAZ) has been initiated in 1997
The ISAG personnel performed an analysis that supports the selection of the input process parameters and setpoints as well as developed an accident analysis for DAZ Safety Case
DAZ Project (2)
It was shown that in case of transients with failure of existing Control and Protection System but with actuation of DAZ system reactor is adequately protected and any safety criteria are not violated
After implementation of DAZ system at the Ignalina plant ATWS would be moved from the beyond design basic accidents to the design basic accident class
The DAZ system is already implemented at Unit 1 and will be implemented at Unit 2 in 1999